How to calculate MRO man-hours per AMC1 145.A.30(d)

ManHourPlan methodology guide · ~8 min read · Written by an active AW139/AW189 type instructor

Every EASA Part-145 maintenance organisation must produce a man-hour plan showing that it has enough staff for the work it commits to — and keep that plan honest as reality diverges from it. Yet ask ten maintenance managers how their number was calculated and nine will point at a spreadsheet built by a predecessor. This guide lays out the complete, defensible method: the same one implemented in our free man-hour calculator.

What AMC1 145.A.30(d) actually requires. The organisation must establish a man-hour plan for the anticipated maintenance workload, derived from the work to be performed. The plan must be reviewed and updated — in practice at least every quarter — and a shortfall of available man-hours against plan exceeding 25% in a month is a significant deviation that must be reported through the compliance monitoring system. Auditors ask for the plan, the review records, and the derivation of the numbers.

01Workload: what the fleet demands

Start from physics, not headcount. Each aircraft generates scheduled and unscheduled (line + defect) workload:

workload = qty × FH/yr × [ (check MH ÷ interval FH) + line coeff ] × (1 + defect %)

Type coefficients differ significantly — a 600 FH/interval, 250 MH check on an AW139 is not interchangeable with an H135 (≈120 MH) or an S-92A (750 FH interval, ≈450 MH). Use published maintenance-planning data for your types, then calibrate against your own records — surveyors explicitly accept calibrated in-house figures.

02Coverage: what the roster demands

Workload tells you how many productive hours you need. Coverage tells you how many people you need regardless of workload — the minimum presence to hold an AOC/approval:

coverage headcount = min manning × shift multiplier × rotation factor
Offshore? IOGP-690 §25C sets engineering duty expectations your oil & gas customers audit against: 12-hour duty cap, 10 hours rest, 7 days off per month, and a documented man-hours-per-task process. Your rotation factor must be consistent with those limits — a 24/7 position staffed on permanent local terms is arithmetically impossible and a red flag in customer audits.

03The establishment: take the maximum, then add group functions

Per base, the true requirement is the higher of workload-driven and coverage-driven demand. Under-coverage shows up as audit findings; under-workload shows up as the 25% deviation. Then add the functions that don't turn wrenches:

04Worked example — 5 × AW139, single base

ElementValue
Fleet: 5 × AW139 @ 450 FH/ac/yr2,250 FH/yr
Scheduled: (450/600 × 250) + (450/2400 × 1800) per ac525 MH/ac
Line: 450 × 1.2 MH/FH per ac540 MH/ac
Defect allowance (15%)+160 MH/ac
Total workload (5 ac)6,125 MH/yr
By workload ÷ 1,500 productive h/yr4.1
By coverage: 3 min × 2 shifts × 1.257.5
Performing requirement (max)7.5
+ Supervision (15%), planning, compliance+3.1
Total establishment≈ 11

Note how the answer is coverage-driven, not workload-driven — a result that surprises managers who size teams from check hangar loads alone. This is exactly the number an auditor probes: "why 11?" With this derivation, the answer is one page long.

05Operate the plan: monthly deviation, quarterly review

Do this in minutes, not days