Staffing · Training Pipeline

New-hire training pipeline: why your March recruit won't save your July checks

ManHourPlan Blog · 2026-10-31 · ~6 min read · By an active AW139/AW189 type instructor

I teach the type courses your new hires sit in, so let me say the quiet part: the day HR sends the offer letter is not the day your manpower problem starts shrinking. Between "welcome aboard" and "authorised to certify on type" there is a 9–12 month pipeline — and if your man-hour plan counts a recruit at full strength from month one, the plan is lying to you by exactly the amount that will hurt in the peak season.

01The pipeline clock, honestly

Here is a realistic timeline for a licensed B1 joining your organisation without the AW139/AW189 rating — the common case, because fully type-rated engineers with current authorisation rarely sit on the market:

PhaseMonthsEffective output
Notice period & onboarding1–20%
Type course (theory + practical), waiting for a course slot2–40%
Supervised consolidation on the line/hangar4–7~40%
Solo mechanical work, not yet certifying7–10~70%
Company authorisation assessment & issue10–1290–100%

Two details hide in that table. First, type course slots are the real bottleneck — AW189 and H160 courses are booked out months ahead, and missing a slot slides the whole pipeline by a quarter. Second, the supervised phase is not free: a trainee at 40% output consumes roughly 15–20% of a mentor certifying engineer's time. Two trainees in a hangar during the summer peak can be a net negative on certifying capacity for the first months.

02The worked example: hiring for the July peak

Your base runs AW139s, and next July–August you face two 600 FH checks plus the usual line load. The gap analysis says you're short 720 man-hours across 9 weeks — about 80 hours a week, or 2.2 fully-productive engineers. Management approves two hires "in good time." Define good time:

Hire start dateProductivity in JulyJuly–Aug hours givenCertifying hours
Previous October (9 months ahead)~90%~290Yes — authorised
January (6 months ahead)~40–50%~150No
March (4 months ahead)~30%~100No
May (2 months ahead)~0%~0Net negative (mentor drag)

The March hire — which feels early — contributes barely a third of an engineer and, critically, zero certifying hours during the peak. If your gap is in certification (and during check season it usually is), no hire inside the same calendar half-year fixes it. The formula your plan should use:

required hire date = peak start − (type course wait + course + consolidation + authorisation lead)
typical: peak start − 9 to 12 months, per license category

03Why this keeps going wrong

04What belongs in the man-hour plan

Under AMC1 145.A.30(d) your man-hour plan must reflect realistic availability — and "realistic" includes the pipeline. Three practices that survive audits and July: model every non-authorised engineer at their ramp percentage by month, not at 1.0 FTE; carry a certifying-hours line per category that only counts staff who will actually hold authorisation in the window; and run the hiring trigger backwards — when the plan shows a certifying shortfall in month N, the recruitment decision had to happen in month N−9. If that date is already in the past, the plan should show the shortfall honestly and price the contractor cover instead of pretending the recruit will be ready.

Model hires at their real ramp-up capacity and see the certifying-staff gap month by month — with an auditor-ready PDF for the planning meeting.

Run the scenario →