The quarterly man-hour plan review: a 90-minute agenda that keeps you compliant

ManHourPlan Blog · 2026-11-06 · ~6 min read · By an active AW139/AW189 type instructor

AMC1 145.A.30(d) doesn't just ask for a man-hour plan — it expects that plan to be reviewed and updated, and the industry standard reading of that is quarterly. In audit after audit I've watched the same scene: the surveyor asks for the last four review records, and the organisation produces four signatures on an unchanged document. That's not a review. That's a ritual. Here's the agenda that turns ninety minutes into an actual re-forecast — and the worked math for what it should catch.

01Why the signature-only review fails you

A man-hour plan written in January is built on three assumptions: the fleet's utilisation forecast, the check schedule that forecast implies, and the productive hours per engineer you'll actually get. By the end of Q1, all three have moved. Aircraft fly more or less than planned, a 600h check slides six weeks, two engineers resign and a third goes on long-term sick. The annual document still says "compliant" while the roster underneath it is quietly breaching the 25% deviation trigger — the point where, under AMC1 145.A.30(d), the plan stops describing reality and needs formal revision, not just a noting signature.

The quarterly review exists to catch that drift while the fix is still cheap: a contractor booking, a shifted check slot, an adjusted leave approval. Miss two quarters and the only fix left is a slipped input date.

02The five inputs to bring to the room

Ninety minutes is enough if nobody is hunting for data during the meeting. Before the review, collect:

03The worked Q3 example

A five-aircraft AW139 operator planned 2026 on 60 FH/month per aircraft — 3,600 fleet hours a year, roughly 10,400 man-hours/quarter of maintenance workload against 7 engineers producing ~1,600 hours/quarter each after the availability waterfall (11,200 available). Comfortable on paper.

Quarterly review metricPlanQ3 actualDeviation
Fleet utilisation (FH/month)300378+26%
Workload (man-hours/quarter)10,40013,100+26%
Productive hours/engineer/quarter1,6001,430−11%
Available capacity (7 engineers)11,20010,010−11%
Coverage ratio (capacity ÷ workload)1.080.76shortfall

Both dials moved at once — demand up 26%, capacity down 11% — and the coverage ratio collapsed from 1.08 to 0.76. Neither movement alone would have breached the plan; together they need roughly 3,090 man-hours, i.e. about 2.2 additional engineers, from Q4 onward. A signature-only review misses this because each number, looked at in isolation, "sort of" matches the plan.

required headcount = forecast quarterly workload ÷ actual productive hours per engineer
13,100 ÷ 1,430 = 9.2 → plan for 10, not the 7 on the roster

04The 90-minute agenda

05What the surveyor wants to see

The audit question is never "did you meet quarterly?" It's "show me a review that changed something." One review record with a deviation found, an action taken, and a versioned plan update is worth more than four clean signatures. If your last four reviews genuinely found nothing, that is itself a finding — it means the review isn't recalculating anything.

Run the re-forecast before the meeting: update utilisation, log actual hours, and see required headcount, deviation flags and the coverage ratio recalculated — with an auditor-ready PDF for the review record.