Holiday leave vs the December check stack: the man-hour math for year-end
July breaks your plan with volume of leave. December breaks it differently: public holidays, burn-down leave and the year's last check stack all land in the same four weeks — and half your customer deliveries are contractually "before year-end". Here is the capacity formula I make every planning class run in October, with the numbers from a real-shaped 14-engineer hangar.
01Why December is not just "another month"
Three drains hit simultaneously, and they multiply rather than add:
- Public holidays. Christmas and New Year typically remove 3–4 working days, depending on how the calendar falls. That is up to 20% of the month gone before anyone takes a day of leave.
- Burn-down leave. Use-it-or-lose-it policies push untaken annual leave into December. In most hangars I've worked, December carries the highest leave density of the year after August.
- The year-end check stack. Calendar-based inspections (12M, 24M) scheduled from entry-into-service dates cluster at year-end, and customers want aircraft back on the line in the first week of January.
The trap: your annual man-hour plan averages all of this away. December never looks like a twelfth of the year on the ground.
02The December capacity formula
− booked leave hours − standing line/AOG cover
Worked example — a 14-engineer Part-145 maintaining AW139s and AW189s, December 2026 (23 weekdays, 3 public holidays):
| Capacity line | Calc | Man-hours |
|---|---|---|
| Gross availability (20 workable days) | 14 × 20 × 8 | 2,240 |
| Productive hours at 70% wrench-time | 2,240 × 0.70 | 1,568 |
| Booked leave (avg 5 days each, productive-adjusted) | 14 × 5 × 8 × 0.70 | −392 |
| Standing line/AOG cover (2 engineers continuous) | 2 × 20 × 8 × 0.70 | −224 |
| Net December capacity for scheduled work | 952 |
Now the demand side already committed for December: one AW139 600 FH/24M check at 1,500 MH and one AW189 200 FH inspection at 450 MH — 1,950 MH against 952 MH of net capacity. You're short roughly 1,000 man-hours, about six engineer-months compressed into four weeks, before a single finding is raised.
03The certifying-staff pinch is worse than the headcount pinch
Headcount shortfalls can be softened with contractors. Certifying coverage cannot — a contractor B1 still needs type, company authorisation and recency. In the example above, if two of your four AW189-rated certifying staff have the same week booked off (they will — their kids have the same school holidays), the AW189 inspection doesn't slow down. It stops at every certification gate. Plan certifying coverage by week and by type, not by month and by category.
04Four moves to make in October, not December
- Pull the check forward. A 600 FH check with ±10% interval flexibility can usually start mid-November. Moving 1,500 MH into a 22-working-day month with low leave density is the single cheapest fix you have.
- Cap concurrent leave per license category. A blanket "two people per bay" rule lets both AW189 certifiers vanish simultaneously. Cap by type rating, not by bay.
- Book contractors against the gap, not the headline. The gap is 1,000 MH in four weeks — that is six contractors for the full month, not "a couple of extra pairs of hands for the check".
- Re-run the plan when leave gets approved. Every December leave approval in November is a change to your AMC1 145.A.30(d) manpower position. Treat it like one.
December doesn't surprise hangars that run this formula in October. It surprises the ones still planning on annual averages — and the 25% deviation rule doesn't care that it was Christmas.