The H160 arrives with zero history: man-hour planning for a brand-new type

ManHourPlan Blog · 2026-11-08 · ~5 min read · By an active AW139/AW189 type instructor

Your man-hour plan is only as good as its logged history — and a new type has none. No task-card actuals, no findings ratio, no unscheduled burden, and usually no certifying staff yet. I've watched organisations sign an H160 entry-into-service date with a staffing plan built on the sales brochure's maintenance figures. Here is the method that survives contact with the first year of reality.

01Why "the OEM number" under-plans year one

The maintenance planning document gives you task-hour estimates from a mature, optimised programme — compiled from design analysis and early operators whose data was cleaned before publication. Three things it does not include:

02The proxy-uplift method

You cannot plan from data you don't have, so plan from the nearest comparable fleet you do have, then apply explicit uplift factors you can defend to a surveyor. Worked example: two H160s entering service, 550 flight hours per aircraft per year, alongside a mature AW139 operation:

StepMature-type basisH160 year-one factorPlanned value
Annual utilisation1,100 FH—1,100 FH
Scheduled burden (proxy MPD rate)2.6 MH/FH× 1.30 learning curve3.4 MH/FH
Scheduled man-hours2,860—3,718
Unscheduled ratio (findings/rectification)+40% of scheduled+60% (infant mortality)+2,231
Total year-one demand4,004 MH—5,949 MH

At roughly 1,300 productive hours per engineer per year (after leave, training and indirect work — the availability waterfall in our AMC1 145.A.30(d) guide), the naive plan says 3 engineers; the honest plan says 4.6, so 5. That is a 48% demand uplift over the brochure math — and it is all in factors you can show an auditor line by line.

year-one demand = utilisation × proxy rate × learning uplift × (1 + infant-mortality findings ratio)
1,100 × 2.6 × 1.30 × 1.60 ≈ 5,950 MH → 5 engineers, not 3

03Certifying staff: the six-month head start nobody budgets

Manpower is divisible; certification is not. A B1.3 or B2 certifier needs the type course, then OJT on the actual aircraft, then company authorisation — a pipeline of four to six months that cannot start before course slots exist. For the two-aircraft example above, assume certifying involvement on 25% of the 5,949 hours — about 1,490 certifying man-hours. Two freshly rated certifiers, each able to spend perhaps 35% of their productive year certifying while also working the floor, deliver roughly 900 hours. You are 40% short on the one resource you cannot subcontract at short notice. The fix is unglamorous: send three people, not two, on the first courses, and schedule the second course wave before entry into service, not after the first AOG night.

04Treat year one as a live re-forecast

The uplift factors above are planning assumptions, and AMC1 145.A.30(d) expects you to test assumptions against actuals. Log task-card actuals from day one, compare them against the proxy rate every quarter, and collapse the uplift factors as real data arrives — most fleets reach the mature rate between months 12 and 24. If actuals run hotter than the uplifted plan, you are in deviation territory and the quarterly review is where you catch it, not the audit. The organisations that get new-type introductions right are not the ones with the best guess — they are the ones who wrote down the guess so they could correct it.

Model the new type before it lands: set the proxy rate, apply your uplift factors, and see headcount and certifying coverage in numbers — with an auditor-ready PDF for the EIS planning meeting.

Run the scenario →