Dual-rated B1/B2 coverage: one licence is not two people
A dual-rated engineer is one of the best assets in a helicopter maintenance organisation. On paper, that person fixes both sides of the roster: one more name under B1, one more under B2. In the hangar, the same name creates a quieter constraint: the licence can move between categories, but the person cannot occupy both at once. If your man-hour plan does not model that concurrency limit, your release day is built on borrowed time.
01Count licence seats, then person-hours
The first pass is simple: who can legally certify which task? That gives you B1 coverage and B2 coverage. The second pass is where plans fail: how many productive certifying hours does each physical person contribute on the day those tasks must be released?
Use six productive hours per eight-hour shift for certifying work after briefings, access delays, paperwork and supervision. A dual-rated engineer therefore contributes six flexible hours — not six B1 hours plus six B2 hours.
B1 hours + B2 hours ≤ that same total
02The release-day worked example
Take an AW139 600 FH/24M check approaching release. The final inspection and rectification window needs 14 B1 certifying hours and 10 B2 certifying hours in one day. Your available crew is two B1-only engineers, one B2-only engineer and one dual-rated B1/B2 engineer:
| Certifying resource | People | Productive hours | B1 allocation | B2 allocation |
|---|---|---|---|---|
| B1-only | 2 | 12 | 12 | 0 |
| B2-only | 1 | 6 | 0 | 6 |
| Dual-rated | 1 | 6 | 2 | 4 |
| Available vs demand | 4 people | 24 | 14 / 14 | 10 / 10 |
The day fits with zero slack. The dual-rated engineer spends two hours on mechanical certification and four on avionics. One avionics retest, one late panel or one additional snag moves an hour from B1 to B2 — and B1 falls to 13 hours against 14 required. The aircraft misses the release window even though the roster appeared to contain three B1-capable and two B2-capable people.
03Add the release-day reserve
For AMC1 145.A.30(d) planning, apply a reserve to peak certification days. I use 20% as the starting point, then adjust from your own findings history:
- B1 reserved demand: 14 × 1.20 = 16.8 hours.
- B2 reserved demand: 10 × 1.20 = 12 hours.
- Residual after single-rated staff: B1 needs 4.8 dual-rated hours; B2 needs 6. Total dual-rated demand = 10.8 hours against six available.
The fix is not automatically another permanent engineer. Move four hours of B2 work to the previous shift, and the padded B2 demand becomes 7.2 hours. The B2-only engineer covers six; the dual-rated engineer covers 1.2, leaving 4.8 for B1. Both categories now meet their reserved demand with the same four people.
The sequencing matters as much as the headcount. Put avionics built-in tests and software loads ahead of the final mechanical close-out where the maintenance programme allows it, and hold the dual-rated engineer back as the flexible reserve. If you spend that reserve early, the last four hours of the input become dependent on every task card arriving exactly on time — which is not how helicopters behave.
04The planning rule that survives audit
In the man-hour plan, show dual-rated staff twice for qualification coverage, but once for daily capacity. Then schedule category demand by shift, allocate dual-rated hours to the residual after single-rated staff, and record any day where the flexible allocation exceeds 80% of their productive shift. That day is a release risk, a fatigue risk and a contractor trigger — before the aircraft is due out, not after.
Model B1, B2 and dual-rated coverage separately, test the peak release day, and export an auditor-ready manpower plan your roster can actually deliver.
Test your coverage →