AW139 vs AW189 man-hour planning: why one plan can't crew two fleets

ManHourPlan Blog · 2026-11-01 · ~6 min read · By an active AW139/AW189 type instructor

I teach both types, so I get this question a lot: "We added two AW189s to our four AW139s — can we just scale the man-hour plan by flight hours?" The honest answer is no. The two airframes look like siblings, fly similar offshore profiles, and share a type-course classroom for a week — but they generate different man-hour loads per flight hour, different check packages, and non-transferable certifying authorisations. A fleet-average plan hides all three.

01The three ways the types diverge

02Worked example: six-aircraft offshore fleet

Take a typical mixed offshore operator: 4 × AW139 flying 1,200 FH/year each, 2 × AW189 flying 1,400 FH/year each. Build the annual demand per type:

Workload driverAW139 (4 ac)AW189 (2 ac)Fleet total
Annual flight hours4,8002,8007,600
Line MH per FH2.22.7—
Line maintenance MH/yr10,5607,56018,120
600 FH checks per year8~4.7~12.7
MH per check1,5002,000—
Base maintenance MH/yr12,0009,40021,400
Total MH/yr22,56016,96039,520

Now run the shortcut your spreadsheet wanted to take: fleet average of 2.38 MH/FH applied to 7,600 hours gives 18,100 line man-hours — looks fine. But apply that average to the AW189 fleet alone and you've budgeted 6,660 hours against a real need of 7,560. You've under-crewed the AW189 by ~900 man-hours a year (~12%) — before a single base check is counted.

per-type demand = (FH × type-specific MH/FH) + (checks × type package MH)
never: fleet FH × fleet-average MH/FH

03The certifying-staff side of the same problem

Convert those hours into people per license category, per type. At roughly 1,600 productive hours per engineer-year, 39,520 man-hours implies about 24–25 engineers overall. But the split matters: if only four of your B1s hold the AW189 rating, the AW189's ~17,000 annual hours have to flow through those four authorisations — and two of them are on rotation at any given time under offshore rosters. The moment one goes on leave or type recurrent, the AW189 line is one sick day from an AOG with nobody legal to sign. This is why the man-hour plan under AMC1 145.A.30(d) must show staff by qualification, not just headcount.

04The practical fix: plan per type, pool the slack deliberately

Do the per-type arithmetic once and the mixed fleet stops being mysterious: you can see exactly which type is driving the next staffing conversation.